Back to news

Important information

Late in the evening on Tuesday the 31st of August, an accident occurred in the wind farm when a blade broke on turbine Björkvattnet 20 (BJV20). No people were injured in the accident. The root cause analysis has been initiated together with the supplier of the turbines to be able to determine the reason for the failure.

 

We have set a temporary safety distance around the affected turbine (Björkvattnet 20 – BJV20) of 250 meters. The road leading up to that specific turbine has been blocked temporarily. Please contact Jonathan Voisin on +46 733 24 38 18 if you have any questions. We apologize for any inconvenience that this might cause.

Back to news

July 2021 Update

The summer season is now underway at Björkvattnet this month.  It has brought fair weather and the holiday period in Sweden. A new single blade lifting device arrived on site at the beginning of July, and the final blades were successfully installed on the last turbine.  This concluded the main installation works for all thirty-three (33) turbines in the wind farm.

The final five (5) customer walkdowns were carried out this month, which sees the turbines inspected inside and out.  Any remedial works identified or items requiring attention are flagged up to the Contractor as ‘snags’ to be actioned in the coming weeks.

This month saw the commencement of the re-instatement works, which includes the dismantling and removal of the stoned area which had been used for storage of materials.  Works were carried out this month to prepare the turbines for a planned grid outage which started on the 27/07/21.  During the period of the grid outage, no power will be imported or exported, so 24hour tests and eight-day performance tests cannot be carried out on the turbines during this period.  The turbines were placed in a safe position prior to the outage and will remain like this for the duration, which is expected to finish 07/08/21.

 

This month saw a further one (1) turbine commissioned, and four (4) complete their reliability run.

 

To summarise the status, main Installation is complete on all thirty-three (33) turbines; commissioning works have been completed on thirty-one (31) turbines; and thirty-one (31) turbines have completed their reliability run, the 8-day performance test and final stage before the turbine is considered operational. The Centre and South-East areas of the wind farm have achieved operational completion, which equates to two of the five sections of the wind farm.

 

August will see a continuation of internal works, commissioning, and test runs as well as a continuation of the re-instatement works.

Back to news

June 2021 Update

June saw the last of the heavy fall weight testing which had been carried out throughout the thaw period.  The test results were used to assess the bearing capacity of the ground to ensure heavy machinery could continue to operate safely.  The last tests on the crane hardstand area in June, showed that all frozen water was gone from the top two metres of ground.

 

As works are coming to an end and the construction phase of the project is in its latter stage, Björkvattnet welcomed representatives from The County Administrative Board (Länsstyrelsen) who visited site in June to carry out a routine inspection.  The site visit was very well received and positive, and Björkvattnet will continue to work closely with Länsstyrelsen until the project is fully completed.

 

The de-mobilisation operation continued this month with materials, machinery and storage containers being removed from site.  The site compound and offices are also being reduced to reflect the smaller team size as less people are present on site each day.  Only the blades remain to be installed for the final turbine to be fully erected and this will be carried out once a newly manufactured single-blade lifting device is delivered to site.

 

This month saw a further two (2) turbines commissioned, and two (2) complete their reliability run.

 

To summarise the status, main Installation is complete on thirty (32) turbines; commissioning works have been completed on thirty (30) turbines; and twenty seven (27) turbines have completed their reliability run, the 8-day performance test and final stage before the turbine is considered operational. The Centre and South-East areas of the wind farm have achieved operational completion, which equates to two of the five sections of the wind farm.

 

July will see a continuation of internal works, commissioning, test runs, and installation of the blades for the last turbine.

Back to news

May 2021 Update

The thaw period has finally passed at Björkvattnet. The ground conditions were being closely monitored and inspected during the thaw period to ensure heavy machinery could continue to operate safely.  The geotechnical engineers have been monitoring the ground temperature at crane hardstands with in-ground measurement rods and the latest results of the heavy fall weight testing, supplemented by visual inspection, shows the thaw is now complete and bearing capacity is suitable.

 

The team at Björkvattnet have been busy tidying up the site this month, removing materials and machinery that are no longer required on site.  As there is now only one turbine that requires installation, two of the three main cranes (used to erect the turbines) have been dismantled and removed from site, and most of the installation team have de-mobilised from site and moved onto other projects.

 

This month saw a further two (2) turbines installed, four (4) turbines commissioned, and seven (7) complete their reliability run.

 

To summarise the status, Main Installation is complete on thirty (32) turbines; commissioning works have been completed on twenty eight (28) turbines; and twenty five (25) turbines have completed their reliability run, the 8-day performance test and final stage before the turbine is considered operational. The Centre and South East areas of the wind farm have achieved operational completion, which equates to two of the five sections of the wind farm.

 

June will see a continuation of internal works, commissioning, test runs, and installation of the final components for the last turbine. Also, operational completion of the South Centre and South West sections are expected to conclude. June should also see final civils works to leave the wind farm in its finished state, including the removal and reinstatement of the on-site storage area.

 

 

Back to news

April 2021 Update

Spring has arrived at Björkvattnet, the weather has been milder throughout April and the snow is beginning to recede.  As breeding season is now underway, the local wildlife has been spotted at the wind farm with an abundance of grouse and capercaillie roaming throughout the site.  The better weather, although positive in many aspects, also brings considerable risk when using the heavy machinery used to lift and install the turbines.  The ground conditions are being closely monitored and inspected each week by the geotechnical engineering team to ensure that work continues safely.

 

As installation works near their end at Björkvattnet, this month has seen the installation teams demobilise from site and be redeployed onto other projects.  One of the main cranes (used to erect the turbines) has left site and another is de-rigged and dismantled, ready to be taken away from site.  This leaves only one main crane in place ready to carry out the installation of the final turbines.

 

This month saw a further four (4) turbines installed, six (6) turbines commissioned, and five (5) complete their reliability run.  Operational completion was achieved for the Centre and South East sections.

 

To summarise the status, Main Installation is complete on thirty (30) turbines; commissioning works have been completed on twenty four (24) turbines by the end of the month; and eighteen (18) turbines have completed their reliability run, the 8-day performance test and final stage before the turbine is considered operational.

May will see a continuation of internal works, commissioning, test runs, and the final turbine erections. Also, operational completion of the South Centre and South West sections

Back to news

March 2021 Update

Throughout the month of March, we have seen signs of the arrival of Spring. Weather is always important during the construction of a wind farm, and although it might be obvious that wind and snow can impact construction, warming temperatures also play a role in climates similar to that of Björkvattnet. The heavy transport and lifting equipment must have a solid foundation to work upon, and as the frost begins to thaw, the ground’s capacity to withstand construction loads could potentially be compromised. To ensure that we continue to operate safely, load bearing sections of crane hardstands (where the cranes lift and install the turbine components) are being continually monitored by a third-party geotechnical engineering team. This month saw a further three (3) turbine installed, four (4) turbines commissioned, and three (3) complete their reliability run.

 

To summarise the status, Main Installation is complete on twenty-six (26) turbines; commissioning works have been completed on eighteen (18) turbines by the end of the month; and thirteen (13) turbines have completed their reliability run, the 8-day performance test and final stage before the turbine is considered operational.

 

April will see a continuation of turbine erection, internal works, commissioning and test runs. Also, operational completion of the first section.

Back to news

February 2021 Update

February, already being the shortest month, did not hold much promise in terms of progress as high winds and snow persisted throughout, making life difficult for the installation teams, with a further one (1) turbine being installed. Despite this, commissioning works, and turbine reliability runs continued well, simultaneously testing the performance of the turbine while beginning to export electricity to the grid. Three (3) further turbines were commissioned, and six (6) completed their reliability run.

 

To summarise the status, Main Installation is complete on twenty-three (23) turbines; commissioning works have been completed on fourteen (14) turbines by the end of the month; and thirteen (13) turbines have completed their reliability run, the 8-day performance test and final stage before the turbine is considered operational.

 

The fallen crane reported last month was safely disassembled and removed from site. Ground material around the crane was collected and analysed and results indicated that there is no residual concern to the health of people or the environment. The incident was formally reported to LST. The site roads are once again clear, and installation works can continue unhindered.

 

March will be a continuation of turbine erection, internal works, commissioning, test runs, and we should see more turbine arrays enter the operational phase.

Back to news

January 2021 Update

The installation teams returned to site in early January following a winter break, with all site staff following the government and site specific Covid-19 protocols upon arrival. Snow clearance continued throughout to allow commissioning and servicing teams to access turbines, however, the installation teams’ first task was to clear the crane pad area and components of snow and ice to allow for the safe continuation of works. Ice and snow build-up can inhibit component lifting, as well as pose a safety risk with the increased potential for falling ice; on such tall turbines this is carefully mitigated. On the turbine blades, when stationary, snow and ice build-up can also potentially hinder the commissioning phase, by adding weight. However, when it comes to commissioning, wind also has an important role to play, as it is needed to ‘kickstart’ the turbines, producing its own energy which power some commissioning tasks. This month, the wind arrived either too strongly, or not at all, disrupting progress on this front. In addition, we had a crane incident on January 12, which had no injuries nor observable environmental damage, but has delayed installation activities. When the weather is not favourable for installation or commissioning, site personnel can assist in other areas of development, such as pre-assembly works on turbine components and mechanical and electrical fit-out inside the erected turbines.

 

To summarise the status, Main Installation is complete on twenty-two (22) turbines; commissioning works have been completed on eleven (11) turbines by the end of the month; and Seven (7) turbines have completed their reliability run, the 8-day performance test and final stage before the turbine is considered operational.

 

February will be a continuation of turbine erection, internal works, commissioning, test runs, and we should see more turbines enter the operational phase. We are also expecting a delivery of a single set of blades to the site, expected to arrive in February, but without forecast of an exact date.

Back to news

December 2020 Update

The November winds seemed to settle as we entered December, allowing for a more productive month at Björkvattnet Wind Farm. The cooling weather did, however, bring with it some tricky conditions, as snow and ice began to build-up on and around components. The installation teams quickly learned to navigate this, and once snow and ice build-up had been cleared from components the installation teams have continued to erect turbines, completing five (5) in the month, taking the total number to twenty-two (22) for the site. ‘Mechanical Completion’, the term for completion of internal works, has been reached in a further four (4) turbines during the month, taking the total to eighteen (18).

 

Commissioning works have been completed on eight (8) turbines by the end of the month. Six (6) further turbines entered their reliability run, the 8-day performance test and final stage before the turbine is considered operational. Three (3) further turbines have passed their reliability run during the month, bringing the total number of operational turbines to four (4).

 

January will be a continuation of turbine erection, internal works, commissioning, test runs, and we should see more turbines enter the operational phase.

 

Back to news

November 2020 Update

Further winds battered the Björkvattnet region during the month of November, resulting in over 70% of installation windows closed due to weather.  Each component has a wind speed limit, beyond which, it becomes unsafe to lift with the crane due to the lack of surrounding shelter. Therefore, it becomes increasingly more difficult to install higher components with the accuracy required. Since the wintry weather has arrived in earnest, snow clearance and de-icing of components is eating furthermore into the installation windows. However, during the favourable weather windows in November, GE Ren have managed to complete erection of a further four (4) turbines, taking the total number to eighteen (18) for the site.

 

Internal works to fit out the turbines largely remains unimpacted by weather and steady progress has been maintained in this regard. ‘Mechanical Completion, the term for completion of internal works, has been reached in a further eight (8) turbines during the month, taking the total to fourteen (14).

 

Once turbines are considered Mechanically Complete, the commissioning process begins. This is a final check to ensure that all systems within the wind turbine are in working order and, after passing relevant testing, the wind turbine is ready to produce and export power. Commissioning works have been completed on five (5) turbines during the month. Following commissioning works, the turbine undergoes a 24h test, where any issues will be picked up. Once the test is passed, and any issues resolved, the turbine can commence its reliability/test run. The reliability/test run lasts just over a week, where the performance of the turbine is assessed against acceptance criteria and, upon completion, the turbine is considered to be operational. The first turbine entered a reliability/test run towards the end of the month.

 

The delivery of escorted heavy loads to the wind farm was concluded during November, which will reduce the volume of traffic on the public roads and end any potential disturbances the vehicle traffic may have caused. This is an important milestone to achieve ahead of winter road conditions.

 

December will be a continuation of turbine erection, internal works, commissioning and test runs. This means the blades of the turbines will be spinning in order to capture the wind to generate electricity. Turbine operation continues after reliability run without stopping. Over time, more and more turbines will become operational as they successfully come out of their reliability runs, continuing to spin and generate electricity.